top of page
  • Writer's pictureOwen-Ames-Kimball Co.

Construction Heatwave: July's Hottest Projects

Early Childhood Center (ECC)

Inside the ECC, crews are working hard on drywall finishing, fire suppression systems, electrical rough ins, and ductwork, while outside there is still plenty going on with the installation of siding, facia and exterior paint.


Early Elementary and Later Elementary Projects

Other projects underway on the elementary campus include a new roof, carpeting and 2-classroom addition at the Early Elementary and a 2-classroom addition and flat roof replacement at the Later Elementary.


Middle School Projects

Projects underway over the summer at the Middle School include window replacements, mechanical upgrades, single restroom replacement, and new interior finishes.


High School Tennis Court Renovation

To accommodate the asphalt trucks, concrete aprons were completed on three sides of the tennis courts. The sidewalks were also finished. After rough grading and final grading of the surface of the tennis courts, the eagerly anticipated next step of laying the asphalt finally arrived!


High School Cafeteria Renovation and Expansion

Now that the serving area of the cafeteria has been moved to the new addition, this frees up space for crews to focus on interior renovations and expansion of the cafeteria seating area. Other enhancements include a new, larger walk-in cooler.





36 views0 comments

Recent Posts

See All

Comments


bottom of page